Procurement guidance · 2026-10-21
Preparing an HOCl Generator RFQ: The Documents Buyers Should Send
Organize the application brief, utility information and equipment scope so quotations answer the same project requirements.

An effective request for quotation helps suppliers understand the same project. Buyers do not need every technical answer before contacting Xiaoya, but a consistent set of inputs makes the discussion more focused. Separate confirmed site facts from targets and questions that still need review.
Describe the intended work
Begin with the facility type and the task for which HOCl will be used. Identify the relevant work areas, contact methods and existing operating procedure. If several applications are involved, list them separately. This helps the supplier ask the right questions about solution demand and equipment integration.
State the destination country and any procurement requirements already identified by your team. If a particular document, interface language or inspection arrangement is required, include it at the enquiry stage. The technical and documentation scope can then be reviewed before the quotation is finalized.
Provide a demand schedule
Estimate solution consumption over the operating day and show when demand peaks. List the target concentration and pH where these have been defined by the application procedure. If these values are still under review, identify them as open questions rather than filling in a convenient number.
Describe whether production will feed a collection task, a storage tank or connected use points. Include the expected operating hours and any regular shutdowns. These details help the supplier review generation, buffer storage and delivery as related parts of the project.
Attach the utility and layout information
A recent water analysis, where available, helps explain the source-water conditions. Identify the water source and any treatment already installed. Provide available pressure and flow information at the proposed connection point, together with voltage, frequency and phase for the electrical supply.
A simple layout or annotated photograph can show the available space, access route and intended use points. Identify any tanks, pumps or controls that the site wants to retain. You can attach these records to the enquiry instead of trying to describe every connection in a short message.
Define what the quotation should include
Ask suppliers to identify the generator, water preparation, feed arrangement, tanks, pumps, instruments and connection items included in their offer. Separate optional items and customer-supplied equipment. Include packing, documentation, spare parts, installation guidance and commissioning support where these form part of the purchase.
For inspection and acceptance, describe the checks and records your team needs. Agree the scope for the proposed equipment rather than assuming every function or document is included in a standard package.
Use the selection form as a shared record
Complete the available fields in the Xiaoya Group HOCl Selection Form and add supporting files. Keep a copy with the quotation and later technical clarifications. This creates a consistent project record and makes it easier to see which points have been agreed before placing an order.