XIAOYA · CAPACITY PLANNING

HOCl generator
sizing.

Start with your demand. Translate daily solution use into a production rate. Then check the peak, the storage arrangement and the concentration required at the generator outlet.

Calculate your baseline ↗
One day. Two different capacity questions.
Start of shiftEnd of shift

Daily volumesets the average production requirement.

Peak demandtests direct supply or available buffer.

01 / DEFINE THE VOLUME

Count the solution you need to generate.

Use litres of generated solution at one agreed outlet concentration throughout this worksheet. Add simultaneous users and repeated batches without counting the same volume twice.

Ready-to-use supply

Add the solution dispensed to each task over a day. Record when the largest users operate together.

Dilution before use

Convert use-point demand to generator-outlet volume first. In an ideal no-loss dilution, Vgenerated = Vuse × Cuse ÷ Cgenerated, with both FAC concentrations on the same basis and negligible FAC in the dilution water.

Dosing into process water

Total process-water flow is not generated-solution demand. Target residual alone does not establish the dose: chlorine demand, contact conditions and the delivery system need separate assessment.

02 / DAILY CAPACITY + PEAK CHECK

Build your production baseline.

Available production hours mean hours delivering acceptable solution. Exclude planned shutdowns, cleaning and startup output that does not meet the agreed specification.

Prefilled values are a hypothetical example. Replace them with your project inputs.

YOUR PLANNING RESULT

Daily production baseline300 L/hDaily litres ÷ available production hours
Volume needed from storage during this peak450 Lmax(0, peak withdrawal − baseline production) × peak duration

At 300 L/h, production alone does not meet a 600 L/h peak. At least 450 L of usable solution must be available at the start of this event.

Assumes uninterrupted production at the calculated rate throughout the peak and no delivery losses. This is one event’s volume deficit, not a specified tank size.

03 / CHECK THE SUPPLY ARRANGEMENT

The daily total does not describe the whole shift.

Direct supply

Without a usable buffer, the generator and delivery system must meet simultaneous peak demand at the required outlet specification. A daily average of 300 L/h cannot directly cover a 600 L/h withdrawal.

Generation with storage

A buffer can cover short demand peaks if acceptable solution is already available. Check the full sequence of filling and withdrawal, including the first use of the day and repeated peaks.

For each time interval: ending inventory = starting inventory + acceptable production − withdrawal. Inventory must stay above the usable minimum and below the permitted working level.

Review integrated supply arrangements ↗

WORKED EXAMPLE · NOT AN EQUIPMENT RATING

  1. 2,400 L ÷ 8 h = 300 L/hBaseline production at the agreed concentration.
  2. (600 − 300) × 1.5 h = 450 LUsable inventory drawn down during a single peak.
  3. 450 L ÷ 300 L/h = 1.5 hRecovery time only if withdrawal stops completely. Ongoing use reduces the refill rate.
Usable buffer ≠ nominal tank capacity

Include minimum operating level, level-control settings, headspace and the actual refill schedule. Pumps and pipework still need to deliver the peak flow.

Volume alone is not acceptance

Check holding time, light, temperature, materials and FAC at the delivery point. No universal shelf life or storage loss factor is assumed here.

Review output quality & storage ↗

04 / COMPARE THE SAME OPERATING POINT

Flow and FAC belong together.

Use the generator outlet flow and FAC measured or specified at the same operating point. Multiplying a model’s highest flow by its separately listed highest concentration does not establish a guaranteed output.

L/h × mg/L ÷ 1,000 = g/h of available chlorine, expressed as Cl₂ equivalent. This is not pure HOCl molecular mass and does not determine pH, disinfection performance or application suitability.

A reference from Xiaoya’s supplied configuration

The salt-fed 100 L/h configuration sheet lists 500 mg/L concentration and 100 L/h solution output. On that stated basis, the arithmetic is 50 g/h as Cl₂ equivalent.

05 / MATCH THE REQUIREMENT TO EQUIPMENT

Turn the baseline into a specification.

Use the calculated duty as a starting point. Xiaoya’s proposal should identify the selected configuration and the conditions under which the required output is available.

01

Output at one condition

Specify solution flow, FAC basis and pH together, with feed-water conditions and the acceptance sampling method.

02

Operating availability

Agree startup handling, cleaning, maintenance, expected usable hours and the response to an interruption. Do not add an unexplained universal percentage margin.

03

Feed and site inputs

Compare HCl-fed and salt-fed configurations against local feed availability, water treatment, utilities and the agreed equipment scope.

04

Delivery and verification

Confirm storage, pumps, simultaneous users, controls and use-point measurements. The generator outlet rating alone does not size the distribution system.

DISCUSS YOUR CAPACITY REQUIREMENT

Bring your demand profile.
Build a usable proposal.

Share daily generated-solution demand, concentration, production hours, peak flow and duration. Include your application, country, water source and any existing tank or delivery equipment.

Discuss generator sizing ↗